Renovation Series: Permitting Interlude
In this Interlude of the More For LES Renovation Series, we look at what the permitting process actually felt like from the owner’s side — including the waiting, the unexpected issues, and the mounting question: What is taking so long?
For our project, it took roughly 60 days from closing until we were ready to begin construction. Some of that delay coincided with a transition in management and responsibilities within the co-op, some involved the city and permitting process, and some came from issues that simply had to be addressed along the way.
One of those was the discovery of asbestos in the apartment. Rather than requiring full abatement, we had the option of leaving the material undisturbed and properly covering it as part of the construction process — an approach we ultimately chose.
And then there was more waiting.
The approvals and safeguards involved in a New York City co-op renovation exist for a reason, but delays have a real cost for the shareholder. Until construction can begin — and ultimately be completed — we’re carrying both our current residence and the apartment we’re waiting to move into.
We did what we could to compress the timeline by preparing early, but some parts of the process simply weren’t within our control.
About 60 days after closing, however, we were finally ready to roll.
For more Lower East Side real estate insights, articles, guides, tools, and trusted local service professionals, visit More For LES, and stay tuned for the next episode of the Renovation Series.
—
More For LES video shorts take you inside the Lower East Side—exploring its properties, people, and places through brief, on-the-ground tours. Equal parts insightful and entertaining, the series captures both the standout moments and the everyday details that make the neighborhood a uniquely compelling place to live.
Follow More For LES on YouTube, Facebook, Instagram, and LinkedIn, and subscribe on Substack for deeper insights.